Due to late pile delivery, we were unable to commence piling works on the 05 November as originally scheduled and reported in the last newsletter.

Main piling works will now commence on Tuesday 13 November 2012

The vessel delivering piles to the berth will now arrive on Sunday 11 November 2012 and unloading will take place on Monday.

The delay should not affect the finish date for the piling phase of the works which is expected to be completed in February 2013.

Noise and vibration monitoring arrangements will be put into effect from Monday 12 November 2012 for the duration of the work phase.

We apologise for any inconvenience the works may cause and assure you that completion of the works will be accomplished as speedily and efficiently as possible.

If you have any questions, please do not hesitate to contact me on the numbers shown below.

Eric Smethurst
Public Liaison Manager