We are getting very close to the conclusion of the piling works on the above named project.

At the moment we are driving the last of the tubular piles which could quite possibly be completed today.

The tubular piles are responsible for the secondary “Thud” which has been the reason behind most complaints.

We will have approximately two more weeks of piling on the infill sheets to totally complete the piling works.

Our current section 61 agreement takes us to the end of March and we have applied for and been granted an extension of one week until the 05 April 2013 to complete the driving of the infill sheets.

In order to accelerate the completion of the piling, we have been granted authority to impact drive on Saturday 23 March 2013 for a total of four hours from 0900 until 1300.

Thank you for your patience and understanding during the works.

If you have any questions regarding the work or require clarification, please do not hesitate to call me on the numbers listed below.